UPDATE: We have new estimated dates on our road construction around Verrado. Most of us are frustrated by the “LA-style” traffic these days, but hopefully it will be in our rear view mirrors…just not soon enough! For more development news visit our Community Update news story.
- Verrado Way extension to Canyon Vista will be completed in 2022. This will widen the road to full width from the roundabout to Canyon Vista and include curbing, sidewalk, gutters, etc.
- Indian School from Sunrise Ln to Jackrabbit Trail – Beginning Monday, June 27, crews will begin construction of the medians and re-paving of Indian School Road from Sunrise Lane to the Fry’s shopping center, with a goal of finishing these two important improvements before school starts Aug. 8. During this time, there will be no left turn lanes on Indian School during construction while the barricades are in place. For more information see the 2022 Indian School Rd Widening Project.
- Indian School from Verrado Way to Sunrise will begin construction in 2022 (before Taylor Morrison rental bungalows are occupied.)
- Thomas Road eastbound currently stops at Acacia will complete Thomas Rd to the east side of the wash providing new entry to Verrado from the east will be completed in 2022 (before the new duplexes are occupied).
- Exeter Rd to Indian School Rd will extend Exeter from Pioneer to Indian School, wrapping around the future district park will be built in 2022.
- Verrado Way bridge crossing Lost Creek — It’s the last stretch of Verrado Way not complete and will start construction in 2024.
- McDowell Road and Acacia Way – Construction to begin in 2023. Currently McDowell Rd terminates just east of Verrado Way and will be extended east, to the wash, across the wash and extend the pavement where it currently terminates providing another much needed access to exit the I-10 before Verrado Way.
- Permanent trailhead parking at Canyon Vista — Once the extension of Verrado Way north is complete, a parking lot, just west of Verrado Way, with approximately 70 parking spots will be completed in 2023.
- New District Park Roads – IS Road & Park Street scheduled for completion in 2024. The roads will enable residents to access the new dog park, pickleball courts, skate park, lighted sports fields, party pavilion and restrooms.
Also note that a new cell tower is being planned on Tiger Mountain Drive and Sunrise for 2023. Hopefully this will help the non-Verizon subscribers to get much better cell reception (please).
I understand residents have been promised a skateboard/bike track for approximately eight years. When will construction begin? It is very important that older children have a safe place to ride rather than in the streets.
Construction will begin in 2022 for the future district park located on the north / east side of Indian School Road and Park Street will include a new dog park, pickle-ball courts, a large covered pavilion, restrooms, a skate park/pump track, lighted informal sports fields, and playground equipment scheduled for completion in 2024.
Check out the other upcoming development news at https://verradoway.net/verrado-growth-community-developer-update/