Residential growth
- Regent Hills Phase 2 is currently in preliminary design stage for 53 premium 80 x 130 lots west of Founders Golf Hole No. 15 and south of Lost Creek Drive. Construction of these lots is anticipated to begin Q3 2022.
- Regent Hills Phase 3, a gated neighborhood located west of the Verrado Golf Club, north of Lost Creek and south of West Highlands Drive, is in the planning stage for approx 450 single-family lots. Lost Creek Drive will be extended west and north, connecting into West Highlands Drive. Construction is anticipated to begin in late summer of 2022.
Area road improvements
- The permanent culvert crossing at Park Street, just south of Indian School Road, is in final review stages with the City of Buckeye. Construction is anticipated to begin in Q2 2022.